Aurous Incorporated planned to use $35 of material per unit but actually used $34 of material per unit, and planned to make 1,500 units but actually made 1,300 units. The sales-volume variance for materials is ________.

Respuesta :

Answer:

45,500

Explanation:

1,300 unites multiplied bye 35 unites is 45,500 (hope this helps)